Anyone who reads about OEE will sooner or later come across the figure of 85%. It is often called world class, made up of roughly 90% availability, 95% performance and 99% quality. But is it a good target for your factory?
It depends on your process
An automated line that makes the same products for weeks has different possibilities than a machine park with small batches and many changeovers. With many changeovers, lower availability is logical, and that is not necessarily poor management. A benchmark from another sector therefore says little about your situation.
Compare yourself with yourself
Far more meaningful than an external benchmark is the trend of your own machines. Does OEE rise after you changed the changeover procedure? Does it drop on one shift or for one product? Questions like these lead to actions. A comparison with a figure from an article rarely does.
Be careful steering on the number
As soon as OEE becomes a target, there is a temptation to improve the number instead of the process. For example by not counting planned maintenance or by using a more generous cycle time. So agree on the calculation clearly in advance, and stick to it.
Look at the components
Two lines that both have 70% OEE can have completely different problems. One loses mainly on availability, the other on performance. The improvement action depends on the factor pulling the number down, not on the total. See also Calculating OEE and The six big losses.